Euronext’s datacenter move on schedule despite supply chain issues

Despite chip and hardware shortages, the exchange group says it is on track to go live with the new datacenter on June 6.

Euronext’s relocation from Basildon to its new datacenter in Bergamo, Italy, was met with supply chain disruption that affected hardware delivery and lengthened lead times from manufacturers, sources tell WatersTechnology.

The global shortage of semiconductors used to power everything from computers and cars to datacenters means that in the run-up to the move, Euronext and its client firms ordering hardware for the new site have been waiting for three, six, or sometimes up to 12 months for

Only users who have a paid subscription or are part of a corporate subscription are able to print or copy content.

To access these options, along with all other subscription benefits, please contact info@waterstechnology.com or view our subscription options here: http://subscriptions.waterstechnology.com/subscribe

You are currently unable to copy this content. Please contact info@waterstechnology.com to find out more.

Sorry, our subscription options are not loading right now

Please try again later. Get in touch with our customer services team if this issue persists.

New to Waterstechnology? View our subscription options

Cutting through the hype surrounding the FDTA rulemaking process

A bill requiring US regulators and institutions to adopt a machine-readable data framework for reporting purposes applies to entity identifiers, but not security identifiers, in a crucial difference, writes Scott Preiss, SVP and global head of Cusip Global Services.

Most read articles loading...

You need to sign in to use this feature. If you don’t have a WatersTechnology account, please register for a trial.

Sign in
You are currently on corporate access.

To use this feature you will need an individual account. If you have one already please sign in.

Sign in.

Alternatively you can request an individual account here